As part of the Aviv Park business complex in Zrenjanin, the company Konstruktor designed and constructed four buildings. One of the initial challenges was integrating all four buildings into the broader retail complex of Aviv Park Zrenjanin. Each building designed and built by Konstruktor featured unique technical specifications.

About the project

Building 1, as the most prominent structure, posed significant design and structural challenges due to its irregular ellipsoidal shape and three canopies. The main structural elements of Building 1 consisted of steel profiles (columns, primary and secondary beams).
The structure of Canopy 1 was a steel frame, supported by inclined steel columns. In the section where it extended over the main structure, it rested on the perimeter columns.

Canopy No. 2 featured an ellipsoidal shape and sloped along the longitudinal axis of the building.

Canopy No. 3 was designed as a circular segment and maintained a constant height of 3.60 meters.

Canopies 2 and 3 had a cantilevered Vierendeel-type structure on each façade column, with transverse beams. The roof was a layered system consisting of trapezoidal steel sheeting, thermal insulation, and a waterproof membrane. The façade was built using prefabricated sandwich panels from Brucha, Austria, combined with large glass surfaces.

Buildings 6, 7, and 8 were freestanding units within the complex. Initially planned to have identical purposes, shapes, and areas, these buildings underwent some changes during the design phase. However, all three retained key design elements that connected them — large glazed surfaces, aluminum composite cladding (Alucobond) on canopies, and concrete walls acting as perimeter dividers.

Konstruktor was engaged as the general contractor under a turnkey agreement, responsible for the design and execution of all architectural and structural works, HVAC, hydrotechnical and electrical installations, interior finishing works, and complete landscaping and site development of the complex.

Investor

Aviv Arlon Prima d.o.o.

Location

Zrenjanin

Surface area

Project duration

15.07.2015. - 15.10.2015.